#1 SteveE
Can anyone advise the correct way to notify DNO when installing AIO and Gateway combination with a 6KW invertor supplying them? The G99 fasttrack form does not recognise the GivEnergy AIO or Gateway products.
Can anyone advise the correct way to notify DNO when installing AIO and Gateway combination with a 6KW invertor supplying them? The G99 fasttrack form does not recognise the GivEnergy AIO or Gateway products.
The G99 is an approval process, not a notification like the G98, so this should be pre-approved by your DNO before installation goes ahead. I let my installer deal with this process before my system was installed