We have just had our system commissioned and we now realise this is more complex than we expected. We have a three-phase supply. Our PV array is 30 x SE facing (93%) panels with a 12.45kw potential. We have three 9.5kw GE batteries each with an AC3, one on each phase, and a Huawei string inverter. We use around 18,500kWh annually so we needed to scale up. Now we have to make it work and first impressions of what we need to do are scary.
The electrician who commissioned our system was capable and helpful. His work seems good so far. The issue is that his experience of domestic three-phase and that of the firm supplying the system are very limited.
The first major challenge is to discover just how inadequate GivEnergy’s data management is for a three-phase supply. We have to have an online account for each battery on each phase - three. This makes assimilation of the data on the cloud portal challenging, having to switch between the three account pages all the time. I feel an expansive spreadsheet may be needed.
First impressions of the GE mobile app are that it is worse than useless for a user who has to have three separate accounts. I managed to set the app up on my iPad but the app hangs when you switch accounts - you have to delete it and re-install. I cannot get the app even to work on my iPhone (8). This is because of GE’s need for an overall email username and password plus the underlying three email accounts and passwords for each battery/phase. The app has had a fit and refuses to recognise any login attempts.
Has anyone else got the three-phase blues? Can someone give one or two heads-ups for getting started meaningfully? Am I missing something? Maybe, I am just being a dork?