Hi all,
I have my system installed about a week and a half ago on the 22nd February but it doesn't look like my battery has done it's calibration. It drained to 0 and then charged up to about 4 percent but I was expecting it to charge to 100% like the installer said it would.
It seems to be working in terms of charging when solar is available and when it's below 4% it charges from the grid overnight. It also discharges okay when it has been charged by the sun so I may be worrying about nothing.
I am concerned though that my "Commission Started" and "Battery Calibration" don't have corresponding completion messages so I am worried that my battery won't be able to use it's full capacity as it hasn't done a calibration cycle.
The battery is showing at firmware version 3009 but had started at 3008 so I kind of dismissed the lack of a full charge cycle to a change in the firmware causing it to no longer requiring a full cycle.
Should I get onto my installer to complete the commissioning and to trigger a battery calibration or should I go direct to Givenergy as I guess it will require their systems to do it remotely anyway?
Thanks in advance.