we're planning a new installation but are getting conflicting advice from installers.
Our plan:
6.5kw pv solar
pv inverter (make tbc)
AIO
Gateway
We have existing ASHP & Zappi
Our setup
We want to use the eps capability
External meter cupboard - approx 7m to CU
CU is in boiler room that does not have space for AIO
Plan to install AIO in room next to boiler room - back to back ...on other side of wall from CU
I think this setup should be fairly typical. Needs DNO permission for solar size (very slow in our area!)
One installer is saying the Gateway has to be close to the incoming mains & meter cupboard. In my case externally. Sounds strange?
Another installer proposes installing in vicinity of AIO - which sounds better.
Anyone know if there is a max distance for location of Gateway from incoming Meter?
any other comments or suggestions?