Hello,
Does anyone have an update on when the linking of multiple units will be released? I'm very keen to fit another unit to our existing one. Last I heard was that the software is being tested but that was some months ago.
Hello,
Does anyone have an update on when the linking of multiple units will be released? I'm very keen to fit another unit to our existing one. Last I heard was that the software is being tested but that was some months ago.
JamesFisher22 I too would like an update on this. I really do need to run 2 AIOs.
Does anyone else want this? Please LIKE JamesFisher22 original post or my reply. GivEnergy seems to have scaled back this on the website considerably, except on the final section of the AIO page https://givenergy.co.uk/products/all-in-one/
This WAS the reason I bought the AIO and it appears to be fading.....
I talked to GE at the Everything Electric show on Saturday and was told it is ready for release and imminent.
Brilliant can wait. Hopefully "imminent" means more than "coming soon"😄
Daveb01
I am not sure this answers the question, unless I am missing something here. The point was about having more than one single AIO installed as a unified system, the links you have provided all point to what I have today, a single AIO unit with 13.5kWh of capacity. I am after 27kWh or even more if possible....
My understanding is your installer will order an AIO without the Gateway and wire it up in parallel (eg into the existing AIO). Once this is done the system will see 27 kWh battery.
However GE may need some software/firmware update to allow this to happen on you original AIO
Cheapest I can find today -: GivEnergy All In One - 6.0kW - 13.5 kWh - NO GATEWAY £4,870 +VAT
https://www.itstechnologies.shop/products/givenergy-all-in-one-6-0kw-13-5-kwh-no-gateway

It's not ironed out fully yet I believe but it's not completely plug and play. I'm pretty sure you have to change / add RCDs in the gateway each time you add another.
The parallel ports in the gateway are a decoy, they are not looking like they can be used.
I have just downloaded the newest AIO install manual. Now I know why there are AIO only (no Gateway) for sale. It is not getting ready for the in parallel.
https://givenergy.co.uk/wp-content/uploads/UK-Installation-Manual-All-in-One.pdf