Thought a progress report might be of interest.
Following the sales enquiry, payment of deposit, and site survey, installation was booked for 6 weeks later to fit with our diary.
Day 1 the first to arrive was Travis Perkins with a very large lorry to access a very restricted Court. Before he had unloaded an October van arrived - the first of four.
The installation team arrived in separate vehicles, fitter, plumber and electrician. They needed access to the UFH manifolds upstairs and down. They also need access to the toilet.
First lesson therefore is sufficient parking and toilet provision.
The fitter laid a plastic membrane through out the hallway.
In short order the gas boiler was removed and original plumbing isolated. Outside the fitter assembled a plinth block, set it in the prepared area, and set two mounts, two paving stripes about 6 inches wide on a bed of postcrete or similar. The plinth was filled with gravel (I didn't see and weed suppressant which he might have done) and the ASHP employed and levelled. Our hose reel was refitted.
Inside the plumber installed the hot water cylinder and new pipe work. The first to leave was the electrician, then the fitter, leaving the plumber to set up the hot water system.
It tripped the circuit. Power restored he plugged in the power, no trip, and left the system to heat before departing for the day. When I turned on the hot taps all I got was solder fumed air. Once water flowed it remained cold.
Second lesson, check that the immersion heater is actually drawing power using the GE App.



The battery was charged last night at cheap rate until midnight. From midnight the battery provided for demand. At 0300 the battery was topped up by the grid. Battery top up was available until 0700. The red sector shows grid supply to both battery and ASHP. At 0830 peak demand (3 kW kettle) showed grid supply. Any ASHP demand has been from battery.






