On my G99 provided by my installer it says "Maximum Export Capacity: 5kW". I contacted GE to find out what my export limit is and they replied with 6KW. Does this mean I need to ask GE to reduce the limit to 5kW?
I have a gen 2 hybrid inverter and the 9.5kWh battery. I've never even seen my grid export go much over 3.5kW anyway as we only have 4.8kW of solar panels and the house will usually be using 1kW during the day.
Thanks